Hi Team,

I am facing an issue while importing cost transactions into Project Costing.

Scenario:

  • I created a Purchase Order and performed the Receipt.
  • I created a Miscellaneous Issue transaction.
  • I also created a Movement Request Issue transaction.

All the above transactions are successfully accounted in Cost Management.

When I run Import Costs into Project Costing:

  • Purchasing transactions are getting imported successfully.
  • Miscellaneous Issue transactions are also getting imported.
  • However, Movement Request Issue transactions are not getting imported into Project Costing.

Observation:When I check the Project Transaction Source(Oracle Cost Management) during cost import, I do not see any