Movement Request Issue Transactions Not Importing to Project Costing
Hi Team,
I am facing an issue while importing cost transactions into Project Costing.
Scenario:
- I created a Purchase Order and performed the Receipt.
- I created a Miscellaneous Issue transaction.
- I also created a Movement Request Issue transaction.
All the above transactions are successfully accounted in Cost Management.
When I run Import Costs into Project Costing:
- Purchasing transactions are getting imported successfully.
- Miscellaneous Issue transactions are also getting imported.
- However, Movement Request Issue transactions are not getting imported into Project Costing.
Observation:When I check the Project Transaction Source(Oracle Cost Management) during cost import, I do not see any