Enabling project budget control based on a previous implementation
A client wants to implement the Projects module and would like to use budget control.
Currently, when all settings are enabled, the budget version generated does not use the financial plan type. This is because, in the “Manage Budget Control and Commitment Accounting” settings, it is enabled only for the general ledger, not for both projects and the general ledger. Is there a way to enable this option so that budget control can be activated for projects?