Knowledge: Constrained Plan Putting Resource Requirements on Resource Off Day
Summary:
This video explains why resource requirements can still appear on a resource off day even when a shift exception is defined in the resource calendar. In the demonstrated scenario, the behavior occurs because the resource calendar is used to determine the planned order start date and schedule date, but the resource requirement dates between those points can still be scheduled on valid working days from the organization manufacturing calendar. The video walks through the calendar setup, the planning result, and the date logic that causes resource requirements to appear on an off day.