decrease budget amount

budgetary control is enabled and I created an initial baseline and it's approved , then when I make a budget version andreduce the amount of a specific resource to be less than the previous version I get the error as

The funds reservation process couldn't be completed for the budget adjustment.

the new version is initially set as Submitted when I click create baseline , then it resets back to Current Working

how to enable reducing the amounts ?