Hi Team,

We have a scenario, There is no onhand stock available for a item. Once Generate shipment request job runs its checking the line, since stock is not there the it is not sending lines to 3PL. Instead Shipment status is in "Ready to release" and integration status in "Ready to Interface" with the warning message.

Warning - Non-reserved line not Interfaced

Is there a way we can backorder the shipment line if stock is not there using GSR process?

Please let us know.

Thanks,
Sandhya