Planning a Single Manufacturing Work Order Across Multiple Machines with Different Production Rates
Summary:
How can Oracle Fusion Manufacturing support planning and execution of a single production job across multiple machines that are capable of performing the same operation but have different output rates?
Content (please ensure you mask any confidential information):
We have a manufacturing scenario where multiple parallel machines can execute the same operation. A single production order may need to be processed simultaneously across two or more machines to meet the required production quantity.
Each machine has:
- Different production/output rates
- Different available capacity
- The ability to run the same operation concurrently
Alternative routings allow selection of one machine or routing, but they don't appear to address splitting a single job across multiple machines simultaneously.