Unable to Import OTL timecards to Project Costing
Summary:
Unable to Import OTL timecards to Project Costing
Content (please ensure you mask any confidential information):
Hi Team,
I'm unable to Import approved time cards from OTL to Project costing . import Cost process is not picking any records from OTL side.
Process followed,
- Created and approved time cards in OTL
- Ran process Import costs ,Source oracle time and labor.
But not able to Import the time sheets to Project costing.
From Project Cosing Side : defined the below configs
Rate Schedule
Labor Cosing Rules
Organsation Costing Rules
Expenditure Types
From OTL side : Defined Below configs
HCM Groups
Time Consumer sets
0