Anchor date timestamp in production scheduling
Summary:
We are trying to setup a schedule Horizon of 30 days which includes the Sysdate for scheduling. In order to include the Current sysdate into the Horizon, the anchor date is required to be set as DD/MM/YYYY 08:00 AM. However, according to our requirement, the organization's shift starts by 07:00 AM.
So, when we set the anchor date to 01/07/2026 07:00 AM, the Schedule Horizon starts from 10/Jul/2026 07:00 AM thus excluding the sysdate 09/Jul/2026.
What needs to be done to include the sysdate(09/Jul/2026) with the start time as 07:00 AM to the schedule Horizon.