Capture item actual cost when actual consumption happens instead of at Receipt for Projects.

We are planning to go ahead with the below approach: No Commitments captured as Purchase Receipt cost is not captured. (PDSC Enabled)

  1. Diasable Project Cost Collection at the Project Transaction Source (Purchase Receipt).
  2. Receipt Cost is not transferred to projects.
  3. Items are received to project subinventory.
  4. The same materials are issued to projects using Project Issue trasnaction.
  5. Cost is captured from Cost Management as Misc Inventory Cost.

Need to understand what are negative impacts of this approach apart from Commitments. Any Accounting impact ?