Projects FBDI load - Import Projects - Task Resources
Hello,
I am having issues with the Import Projects FBDI loader.
When trying to load the Task Resources tab in the Import Projects FBDI load - i get an error for the "Resource Type" value. The note indicates the EXPENSE and LABOR are valid values, but we dont see this Resource Type anywhere in the UI when manually updating a task's resource on a project, so I dont know if these values are correct.
Where can I find the values in the Setup? Resource Type isnt mentioned anywhere that I can find, not in the RBS structures or anywhere else I can find.