Why Replenishment Plan recommends Planned Order even though there is an upcoming purchase Order
Summary:
Replenishment Plan is recommending planned order of 50 quantity even when we have an existing 100 quantity purchase order.
Fixed Lot Multiplier = 50
Purchase Order Due date is 13-August-2026
Replenishment Plan has monthly time buckets.
Is this happening because Replenishment Planning internally calculates Planned Orders in daily buckets?
Can adding a Natural Time Fence to items help with this issue or are there any other work arounds?