Award Budget show “Financial plan type” generation source but FPT setup is “Project plan type”?
Summary:
We are using Oracle Fusion Cloud PPM/Grants Management 26B.
The sponsored financial plan type is configured as follows:
- Planning Amounts: Cost only
- Designate as Approved Cost Budget: Enabled
- Enable Budgetary Controls: Enabled
- Generation Source: Project plan type
- Source Plan Type: Project Plan
- Source Plan Version: Baseline
However, when creating an Award Budget using this same financial plan type, the Planning Options page displays:
- Budget Generation Source: Financial plan type
- Source Plan Type: Blank and mandatory
- Source Plan Version: Blank
- Plan Version Status: Blank
- Planning Resource Breakdown Structure: Blank
Based on the financial plan type setup, we expected the Award Budget screen to show: