Award Budget show “Financial plan type” generation source but FPT setup is “Project plan type”?

Summary:

We are using Oracle Fusion Cloud PPM/Grants Management 26B.

The sponsored financial plan type is configured as follows:

  • Planning Amounts: Cost only
  • Designate as Approved Cost Budget: Enabled
  • Enable Budgetary Controls: Enabled
  • Generation Source: Project plan type
  • Source Plan Type: Project Plan
  • Source Plan Version: Baseline

However, when creating an Award Budget using this same financial plan type, the Planning Options page displays:

  • Budget Generation Source: Financial plan type
  • Source Plan Type: Blank and mandatory
  • Source Plan Version: Blank
  • Plan Version Status: Blank
  • Planning Resource Breakdown Structure: Blank

Based on the financial plan type setup, we expected the Award Budget screen to show: