You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

An existing published standard cost was used even though a sourcing rule exists for this item.

Summary:

Hi Team, We are facing an issue on the Cost rollup. We have 7 levels of BOM and each stage has work definitions and proper sourcing rules to rollup the item cost till the Top level item. When we rollup the the cost by creating Cost Scenario with "Supply Chain Cost Rollup Flag" as Yes and by adding top level item as the rollup scope, we are seeing cost is not getting rolled up in all the levels. For stage 3 item we are getting below message
"An existing published standard cost was used even though a sourcing rule exists for this item."