Summary:

I have generated revenue for the project, and I can see the generated revenue at the Financial Summary screen at the contract level.

However, when I check the Project Forecast, the ETC Revenue has not been updated. My financial plan type has the following options enabled:

  1. Include Actual Amounts During Creation
  2. Automatically Update Reported Actual Amounts

For comparison, when costs are incurred against the project, the ETC Cost is updated as expected.

My revenue method classification is Percent Spent.

Could you please advise if there is any additional configuration, setup, or process required for the generated revenue to update the ETC Revenue in the Project Forecast?