Is there a way we can input the Requested Delivery Date on a PO based on PUNCHOUT Item Lead Time?
Summary:
We need to use a supplier's punchout item lead time to influence the Requested Delivery Date on the PO - ideally at the time the PO is created (rather than it defaulting onto the Req). The reason for this is because sometimes a Requisition can be delayed in approval, which would result in an unrealistic Requested Delivery Date.
We have seen similar functionality is available for Master Items and Items from a BPA, although the date is placed onto the Req: - https://docs.oracle.com/en/cloud/saas/readiness/scm/25c/ssproc25c/25C-ssproc-wn-f35729.htm
Is this possible when using a cXML punchout item? The supplier returns the lead time in an extrinsic within the cXML payload, for example: