How to achieve one PO line and multiple schedule for one Item ,

Summary:

How to achieve one PO line and multiple schedule for one Item , when having different requested date and price break exist on BPA

Say a PLO for item A is released for Req date 1/10/2026 —Qty 10

Item B - Req Date —2/11/2026—————-Qty 23

BPA price brk for Item Non Cumulative Qty 10 50 USD

Qty 20 25 USD

Expectation PO **** PO Line 1 Qty 30

Schedule 1 10 1/10/2026 Price 25 USD

Schedule 1 20 2/11/2026 Price 25 USD


Content (please ensure you mask any confidential information):


Version (include the version you are using, if applicable):



Code Snippet (add any code snippets that support your topic, if applicable):