Flow schedule moved to the next day in Production Scheduling — release updates build sequence but no

Summary:

We are using Production Scheduling with Include flow schedules enabled. Flow schedules are sequenced on the production line, including cases where volume exceeds that day’s line capacity or the line is constrained, so some schedules are pushed to the next day.

Scenario

  1. Flow schedules are created in Manufacturing / Work Execution for a given production day (completion date = Day 1).
  2. Production Scheduling refresh/solve reschedules some of those flow schedules to Day 2 because of line availability or capacity constraints.
  3. In the production schedule, the scheduled completion date for those flow schedules correctly shows Day 2.
  4. We then Release the schedule to Manufacturing.