Project Costing is not working as per SLA configured for maintenance work orders resources charges
Issue Summary: -
We are facing an issue where project work order resource charges are not being posted to the correct account that we have mapped in Costing for project-related work orders.
We are creating Maintenance Work Orders with project details by entering the required Project Number, Task, Expenditure Organization, and Expenditure Type. We have different expenditure types for each task under the same project, and we want to derive the account segment value for project costing of Maintenance Work Orders based on the Expenditure Type.
When setting up the Mapping Set under costing for project-specific Work Orders, we have selected Expenditure Type Name as the input source and configured the Mapping Set with the relevant expenditure type values.