Suggested Start Date is calculating incorrectly not same as 'Schedule Ship Date - Post Processing Da

Summary:

Suggested Start Date is calculating incorrectly not same as 'Schedule Ship Date - Post Processing Days'

Content (please ensure you mask any confidential information):

SSD : 25-Nov-2026

Plan Run Date : 10-Nov-2026

Post Processing Days : 3

Suggested Start Date : 10-Nov-2026

Expectation suggested start date : 20-Nov-2026

Version (include the version you are using, if applicable):

26C


Code Snippet (add any code snippets that support your topic, if applicable):