Hi,
We are testing a planning scenario in OTM using Bulk Plan with Cost-Based Routing, with two eligible itineraries for the same orders:
- Itinerary 1: configured with Ground Schedule (shuttle).
- Itinerary 2: standard itinerary without Ground Schedule.
We have two Ground Schedule instances available. There are no itinerary restrictions configured on the orders, so both itineraries are eligible for all orders.
When we run a Bulk Plan for a single order, OTM priorizes and selects the Ground Schedule itinerary as expected.
However, when we run a Bulk Plan for more than one order, OTM selects the standard itinerary without Ground Schedule for all orders