Constrained supply plan: earlier sales order shows Unmet Demand while a later SO is planned
Summary:
In a constrained supply plan, an earlier sales order is left with Unmet Demand Quantity, while a later sales order for the same item and resource is fully planned. The resource has enough capacity for both, and there is no resource overload.
Environment:
- Oracle Fusion Cloud Supply Planning, release 26B
- Plan type: Supply Plan, Supply Planning Mode = Constrained
- Capacity constrained resources: [All resources / Bottleneck resources only]
- Past due sales orders considered: 60 days
- Plan start date: [19/11/2026]
Scenario:
- Resource available 16 hours/day
- SO 1: schedule date 06/10/2026, quantity 408
- SO 2: schedule date 16/10/2026, quantity 840
- Both SOs are inside the past-due window, so both are included in the plan.