Issues with Sending Timephased data from MSP
Hi Everyone,
Are there many customers out there that use the "Send Timephased cost and work data for resources" functionality within MS Project integration? The functionality works in two way such that:
Are there many customers out there that use the "Send Timephased cost and work data for resources" functionality within MS Project integration? The functionality works in two way such that:
- Fiscal GL calendars are recognized, rather than using the Oracle Spread Curves
- If you modify monthly values for resources in MSP, those discrete values are passed to Oracle, rather than using the Oracle Spread Curves