Issue with receiving time-phased data into Microsoft Project (MSP)
However, when we receive the project again from Oracle in order to replan (with or without progress collected), Oracle appears to send the time-phased data back, but MSP is spreading it using the default spread curve of "Flat". Is there any setting in MSP that would allow us to receive the time-phased data from Oracle just like the way it was sent earlier?
Please let me know.
Thanks
Kalyan