Resources - Constrained space - how-to setup
Hi
We have constrained capacity for our sterilization room (3 sq meters) and we can use it only once per week, as sterilization process lasts this long.
When we look at our "Resource workbench", sterilization room does not show, because we set it with a UOM of M3.
We need to know when our capacity for sterilization is overloaded in order to reschedule jobs.
How can we achieve this?
Thanks for your help.
Kelwin