edited Jun 1, 2009 11:13AM in Projects - EBS (MOSC) 3 commentsAnswered
I have created a new Burden Structure and tied that to a new Version of the Composite Schedule.  Labor hours are able to be imported with the PRC: processes without error, but the PRC: Interface Supplier Costs error everytime with the "Can not find burden schedule revision".  Is there a step I am missing?  