Enforce capacity constraints for resource constraints only plan recommends WIP moves inside the PTF

edited Jul 16, 2009 10:59AM in Value Chain Planning - EBS (MOSC) 1 commentAnswered
 We are running a constrained plan (enforce capacity constraints) for resource constraints only.
Overwrite is set to Outside planning Time Fence and Append Planned Order is checked (Yes).

In most cases we are not getting new planned orders inside the Planning Time Fence (PTF) but in
some case we are.  Also we are getting Reshedule In recommendation for WIP Jobs to a date inside the PTF.

Can someone explain how this is supposed to work?

For WIP Discrete Jobs the production schedule for Day 3 is created on Day 2 based on the collected
data and the plan run that happened during the night between Day 1 and Day 2.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center