 I have a question:

If the order is not in MDS and we plan only demand schedule as APS option,  then can we get APS to create cancel recommendations for for WIP jobs in WIP? Here is how I have setup my test case:

  1.  Create sales order for PTO with ATO item
  2.  Run auto configuration and run Final Assembly process
  3.  Load sales orders to MDS
  4.  Launch APS data collection
  5.  Launch APS plan with collected MDS using the "Demand Schedule only" as the planned item
      options from plan option menu
  6.  Release the Subassembly work orders from ASCP workbench
  7.  Cancel the sales order

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center