ASCP Constrained Plan - Recommendations being made inside the PTF. Why?
In most cases we are not getting new planned orders inside the Planning Time Fence (PTF) but in some case we are. Also we are getting Reshedule In recommendation for WIP Jobs to a date inside the PTF.
Can someone explain how this is supposed to work?
For WIP Discrete Jobs the production schedule for Day 3 is created on Day 2 based on the collected data and the plan run that happened during the night between Day 1 and Day 2.