ASCP Forecast Expiration?
I am implementing ASCP Distribution Planning and there is need to setup forecast expiration - the forecast that coudl not been satisfied with supply on "Need by Date" should be ignored by planning.
Please, advise me how to implement such behaviour?
I have found that there is profile "MSO: Maximum Allowable Days Late before Forecast Expiration". It is seemd to be what I'am looking for.
For example, if I set this profile =1, planning allow forecast to be late only one day. But if I set this profile = 0 the planinng engine does not profile value in consideration, the palanning does n't do forecast expiration at all.