ASCP did no calucate the lead times
I have configured a all new setups for ASCP and defined a Constrained Plan with to Capacty constraints. any how when the plan is launced - the parts while looking at sugg start date and sugg completion dates shows same - this means that the ASCP did no calucate the lead times..... when we saw at WIP it shows the correct and lead times are collected.
Iam expecting to see lead times are calucated
Appriciate the help to dubug any setup missing
Thank you - Chandra.