Foreign Currency Billing in Projects
Since billing was the only requirement, we tried enabling multi-currency billing on a USD project. However, we ran into rounding issues even if our bill rate schedule is an even amount. For example even if I have an EUR bill rate schedule of Joe @ 100 EUR per HR, the bill amounts sometimes come out as 100.01. For cost plus projects where it uses a burden schedule, Oracle's taking the USD cost * multiplier * currency rate = Bill Amt which won't work for us. Therefore, I don't think that's an option based on some simple tests.