Projects Intelligence
I have had a SR open for several months on this but not getting anywhere so I thought I would try here and see if anyone can assist. We are on 11.5.10.
We have installed DBI for most modules and working OK, however I am having real problems with the Projects Module.
I have run all the initial loads and after trial and error managed to get it to where I could see figures ok. Have got the truncate and rebuild steps burned into my brain. Note : for anyone starting out on this the incremental refresh of some of the materialised views is so slow they never finish. Still working in this with oracle but as a work-around always run these as a refresh. You will have to manually update the automatic set generated by DBI to do this.