 Hi All

I have setup integrated budgets and have the Budget JNL created from PA to GL however the GL Budget is at Project Header level. There is no option at Task Level,

My client has projects that can go to multiple GL Budgets/ Funding Sources and Ideally Id like to define the GL Budget at Task Level.

Anyone had a similar requirement