Workplan, Progress and Replanning
I am using Fully Shared Structures wp and fp. Entered some actuals and ran summarization to get the actuals into latest published workplan.
I have few questions related to published workplan, actuals, progress collection and replanning.
1) After summarization and with actuals in latest published workplan do we typically enter progress on latest published workplan?
2) Do we typically change the ETC amounts on latest published workplan OR
3) After applying progress to latest working version do we change the ETC and planned amounts in working version
4) Actual Effort ,Actual Cost, Percent Spent and Percent complete are all zeros in published and working workplans in hierarchy view of task. But when I click task details I can see the actual costs and effort. Is it something wrong with hierarchy of tasks?? What exactly is wrong?