For part A which is MPS planned,

In MRP workbench I am able to see one unreleased  discrete job(say no 10),with due date as 5th April,with start date of 30th march with actions as none.

But in MPS workbench I am able to see this same job(no 10) with different due date as 15th April  and start date of 13th April with Actions as Reschedule out

When I am viewing other orders for same part number due dates and start date are same in both MPS and MRP workbench.

(planning time fence is 12 days)

Can anyone please advise why I am getting this discrepancy