Order Placement Date field in Vertical view of colloborative planning not matching with PO Creation
We are facing issue with Order placement field in Vertical view of CP.
Order placement date formula = Supply date - Leadtime.
But in our case PO creation date is 10-APR-2010 .Processing leadtime = 15 days.
Order placement date is coming as 27-jan-2010 which was previous date than PO creation date.
Can any one give some hints on How this feild gets populated and any workaround if some one has already come accross this issue.
Thanks
Vasudha.