Projects - EBS (MOSC)

MOSC Banner

Row 1 Error - Please select a calendar for this project before enabling the Workplan Structure.

edited May 23, 2010 6:49PM in Projects - EBS (MOSC) 3 commentsAnswered
Hi Project Gurus,
I am trying to create a project template and I receive the error "Row 1 Error - Please select a calendar for this project before enabling the Workplan Structure.", when I try to set Set the Final,Workplan and Deliverable options on the Structures tab.

Any one has a clue why?

The Calendar etc have been set at the Implementation Option level so I guess that should not be the issue.

Thanks in advance.

Regards,

Sandeep

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center