Original and Remaining Durations multiplied by 3 in the summary bars
Hi,
Has anyone else come across this before? I have a schedule that is defined in days. When rolling up to a summary bar however, all my original and remaining durations appear to be multiplied by 3 (or near enough).
For example,
ACTIVITY
=======
Start date = 18-Jun-2010
End date = 02-Jul-2010
OD = 14
RD = 14
Calendar = 7day
SUMMARY
========
Start date = 18-Jun-2010
End date = 02-Jul-2010
OD = 43
RD = 43
Any help appreciated as I'm stumped now!
Alan