Regarding Implement From Horizon start date Parameter.
We have uncheked the Parameter Implement From Horizon start date in the EAM parameters form.
Now tried to launch PM schedule for One of the Assets from Maintenance Workbench page.
Since the Paramter is unchecked the start date will be greyed out.
let us say start date is 20-jul-2010. end date 30-aug-2010.
So we expect to create the Schedule between the days. But
1) System is generating Schedule in back date also.
2) Even its an intended functionality , its allowing to implement Which is not correct?
Please check and reply whether any bug is there in R12.