We have our planning calendar setup as  calendar months.  When we enter forecasts they appear on the first day of the month.  The problem is that they appear on the 1st even if it is a weekend or holiday.  When this happens MRP generates unusual messages and demands show on the wrong day.

How to get the forecast to appear on the first working day of the month when using a 'calendar month' calendar?