Import P3 Project to P6 7.1 - Ref. "Budgeted Units"

edited Jul 6, 2010 12:40PM in Primavera (MOSC) 6 commentsAnswered
 When importing a resource loaded project (with "Days" as the planning unit) from P3 into P6 7.1 the budgeted units are always multiplied by 8 regardless of the calendars in the P3 project - what do I need to change in P6 to have it default to multiply by 10 when importing?