Recording Actual and Remaining Units Against Multiple Resources
The issue lies with the Actual and Remaining Units for each Resource. The Actual Units are calculated evenly across each resource versus 50% against the Budgeted Units, which also affects the Remaining Units. Why is this happening, and what can I do to get P6 to calculate the Actual and Remaining Units “correctly”?
Current:
Resource 1 Budgeted Units = 80h Actual Units = 30h Remaining Units = 50h
Resource 2 Budgeted Units = 40h Actual Units = 30h Remaining Units = 10h