Information Across Users not Refreshing
Situation: 2 users in the same file, entering activity status and scheduling project at the same time
Problem: After Refreshing data (F5), activity status information is not being reflected to both users.
User 1 - Activity 100
· Activity shows not started
· No physical or duration % complete (0%)
· Original, Remaining, and At Complete durations match (10 days)
· Budgeted, Remaining, and At Complete Labor Units match (100)
User 2 – Activity 100 (same as User 1)
· Activity shows started – start box checked
· Physical and Duration % complete = 50%
· Actual and Remaining duration match (5 days each) – Original and At Complete durations show 10 days
· Actual and Remaining Units match (50 each) – Budgeted and At Complete Labor Units show