Projects Setup - Labor Cost Rate Schedule LOV do not show the schedule defined with rate schedule ty
I could not select a rate schedule type defined with type Resource class in the Organization labor costing rules
1. Setup -> Expenditures -> Rate Schedules
Define new rate schedule and select rate schedule type as Resource class and enter details
2. Setup -> Costing -> Labor -> Organization Labor Costing Rules
Enter a new rule and the list of values for cost rate schedule do not show up the schedule defined in step1
Can any one explain why the list of values do not allow me to select this schedule type.
Thanks