Necking Summary Bars in P6
I recently sent in s Service request asking if there is a way to show necking for non-work periods in the summary bars (like P3 did). Once again I was told that this will become an "Enhancement Request". Does anyone know of a method wherein I can take activities in an area on the schedule and summarize this area that shows me necking?
Thanks