Free Float calculation in P6
I'm working on a milestone schedule to submit with a bid. Currently I have a completion milestone (finish milestone) that is constrained with a Finish on Date. This milestone is the predecessor with a finish to finish relationship tied to a receive on site date also a finish milestone which is constained the same way as previously discussed. The Completion milestone is on a 5 day calendar and the Reveceived Milestone is on a 7 day calendar. The free float is being calculated on 5 days and shows 84 days. Looking at a calendar there are 118 day between the