Hi Everyone

Request your inputs for the following scenario in planning.
Lets say, currently there are 3 organizations and 1 supplier.

Now for ItemX, onhand quantity is available for ItemX in Org2 & Org3.

When running a supply chain plan MPP (not ASCP) in Org1, can we setup the system to consume the onhand available in Org2 & Org3, before raising a planned order for the supplier as per Sourcing Rule. I guess, what I am asking is, can we do netting considering the onhand in other organizations ? 
How is this handled in ASCP ?

regards,
Sankar.