Total Cost Budget Amount in Project Status Inquiry (PSI)
Hi,
When using multiple user defined budget types for COST BUDGET (in this case none in REVENUE BUDGET),
In Project Status Inquiry (PSI). the field 'Tot - Cst Bgt ' shows only the budget amount for one single budget type and does not sum up the budget amounts from all the cost budgt types.
Inorder to view the budget amounts from other budget types, i need to do the below:
From the Toolbar:
- Tools
- Select the budget you would like to view: Cost Budget Types/Revenue Budget Types
- Select your user defined Budget Type that you want to see.
- The form will rebuild with the correct amounts.
When using multiple user defined budget types for COST BUDGET (in this case none in REVENUE BUDGET),
In Project Status Inquiry (PSI). the field 'Tot - Cst Bgt ' shows only the budget amount for one single budget type and does not sum up the budget amounts from all the cost budgt types.
Inorder to view the budget amounts from other budget types, i need to do the below:
From the Toolbar:
- Tools
- Select the budget you would like to view: Cost Budget Types/Revenue Budget Types
- Select your user defined Budget Type that you want to see.
- The form will rebuild with the correct amounts.