Setup times and Capacity Planning

edited Sep 15, 2010 7:43PM in Manufacturing - JDE1 (MOSC) 1 commentAnswered
 If the machine setup time is set to 1 hour in the Routing (F3003) and if the Work order is for a qty of 10 then does the setup time get multiplied by the WO qty in Capacity Planning

(10*3=30 hours of capacity)? Or will it be 1 hour of capacity?

Where can you setup the fact that setup labor and machine setup does not depend on the Work Order Qty?