Project Management - Stored Custom Measures Help Required
This is my 1st time that i have joined this community. I would require an urgent help.
My Issue:
There is a PO where there is a base value of an item. Now in "PO india localization" form i attach tax categories and taxes and also additional charges such as freight, insurance, etc. When i do receipt the cost that is transferred to the project is the base PO value excluding these additional costs as these costs were added in the INDIA localization form.
Now on my project management dashboard i can only find the cost without the additional chargres. If i want to fetch this additional cost can i use the Stored custom measures to calculate and fetch the values.